TCN, Imcomtel Begin Final Preparations For Katsina Power Substation Upgrade

Markus Habila
Editor

TCN, Imcomtel Begin Final Preparations For Katsina Power Substation Upgrade
The Transmission Company of Nigeria (TCN) and Imcomtel Engineering Limited have stepped up preparations for the next major installation phase of the Katsina 330/132/33kV Transmission Substation Project, following a joint inspection of the facility.
The inspection, conducted on Thursday, September 24, 2026, focused on assessing the readiness of the substation’s civil works, equipment locations and supporting infrastructure ahead of the installation of critical transmission equipment.
Leading the TCN delegation was the Assistant General Manager, Transmission, Katsina Sub-Region, Engr. Usman Idris, who received the Imcomtel team led by Engr. Emmanuel Okafor.
A major focus of the inspection was the site’s two 100MVA power transformers, which were delivered on July 9, 2026.
The teams inspected the transformers and their designated plinths as part of efforts to ensure that the facility is ready for the next stage of installation.
Once fully installed and commissioned, the additional transformer capacity is expected to strengthen electricity transmission within Katsina State and improve the wider North-West transmission network.
The inspection also covered four newly delivered control rooms designed to accommodate critical protection, monitoring and control systems required for the efficient operation of the substation.
TCN and Imcomtel reviewed the readiness of the rooms and other supporting infrastructure, with the exercise providing an opportunity for both teams to identify and address outstanding technical and site requirements.
At the conclusion of the inspection, the two organisations agreed on the final technical requirements and site preparations needed to facilitate a coordinated transition into the next phase of the project.
The development comes as Nigeria continues efforts to strengthen its transmission infrastructure and address constraints affecting the delivery of electricity from generation plants to distribution networks.
The Katsina project is expected to contribute to that effort by expanding the capacity of the transmission network serving the state and neighbouring areas of the North-West.
The TCN inspection team included the Principal Manager, Engr. Mustapha Idowu, alongside heads of relevant technical departments.
With the major equipment already delivered to site, attention is now shifting towards installation and the completion of the supporting works required to bring the upgraded substation into operation.